Ten years of successful and economic activity, countless enthusiastic guests and the still growing demand in all areas formed the foundation for the planning and realisation of the extension building Sonne 2.0. We look forward to an accident-free and smooth construction period and ask for your understanding in case of any inconveniences caused by the construction.
The hotel including restaurant will be closed for three weeks in February 2022. Otherwise the hotel will be open during the entire construction phase.
October 2020 to April 2021
After more than two years of planning, the ground-breaking ceremony for the extension took place on 19 October 2020. In the first stage, the construction of the new goods delivery area will be tackled first. This will be followed by the total renovation of the kitchen. In keeping with the concept of ecological and economic sustainability, the hotel will in future have a lakewater energy supply for heating and cooling.
May 2021 tos April 2022
The actual construction of the hotel and function rooms extension is planned for spring 2021. A spacious hotel reception including lobby and guest lift will offer more space and amenities. A winter garden and a free-flow breakfast buffet are also planned.
October 2021 to April 2022
From autumn 2021 the construction of 3 new rooftop suites can already be started. At the same time a gentle partial renovation of the existing rooms will take place. A photovoltaic system will be installed for the future power supply. In addition to these focal points, the entire façade will be renovated.
Planned opening
With a competent and highly motivated team of builders, specialists, designers and with the support of the entire Balance Familie, we are planning to open the extension Sonne 2.0 in May 2022.
Accompany us on this path of transformation and further development and look forward to the new appearance and gastronomic and tourist lighthouse on Lake Sempach just as much as we do.